INFRASTRUCTURE PROJECTS CY 2018

PROJECT NAME/REFERENCE  APPROVED BUDGET FOR THE CONTRACT  CONTRACTOR CONTRACT AMOUNT NOTICE OF AWARD CONTRACT NOTICE TO PROCEED
Construction of Information Technology Building at OMSC Labangan (B-8661-18-01)
 FIRMABUILT CONSTRUCTION
Construction of College of Engineering, Architecture and Technology Building at OMSC Labangan (B-8661-18-02)
KRBS Construction and Trading
May 28, 2018  June 6, 2018  June 25, 2018
Construction of Overhead Tank with Treatment Facility for College of Agriculture in Murtha Campus
P2,000,000.00
F.A. Torres Construction
P1,999,480.32 June 25, 2018  July 4, 2018  August 15, 2018
Construction of One-Storey/4-Classroom Building at OMSC Labangan
P5,000,000.00
Capitol Builders and Construction Supplies
P4,996,582.47 November 21, 2018 November 28, 2018 December 03, 2018
Riprapping and Drainage System at OMSC Sablayan
P1,560,000.00
Capitol Builders and Construction Supplies
P1,558,070.95 November 21, 2018 November 28,2018 December 03, 2018